Burnsville & the Twin Cities West Metro
Most cities in this area that require a septic compliance inspection attach it to bedrooms, on the logic that a system is sized by bedroom count. Woodland goes further.
The city’s ordinance requires a compliance inspection of an existing system whenever an additional bedroom or an addition to the house is requested. Since the large majority of Woodland homes are on private septic systems, that catches a great many whole-home projects that would sail through unremarked two miles away.
It is not an obstacle. It is a date in the calendar, and the projects that go badly here are the ones where nobody put it there.
Woodland is almost entirely a remodelling market, and the city says so itself — the predominance of building permits issued here are for maintenance and renovation of existing homes, with roughly one new single-family permit a year, almost always replacing a smaller older house on the same lot. Around a third of the housing stock predates 1940.
So the work is what you would expect: houses built modestly on beautiful lots, added to over decades, now being brought up to a standard that matches the address. What differs from a neighbouring city is almost entirely procedural, and there are four items worth knowing before design starts.
The septic inspection is the first. There is a seasonal provision — a request made between 1 November and 30 April can receive a permit immediately, with the inspection due by 1 June and the certificate filed by 30 September — which makes a winter start genuinely available.
The second is coverage, and the numbers are tighter than two-acre lots suggest. On lots over 16,500 square feet the main building may occupy no more than 10 percent of gross lot area, with total impervious including buildings capped at 25 percent. Relief is by variance rather than by conditional use permit, which is a higher bar. Lot area excludes land below the ordinary high water level, wetlands, and road and driveway easements, so the figure you calculate from a deed is not the figure that counts.
The third is the lake setback, which is expressed unusually. For Lake Minnetonka it is the greater of 75 feet from the ordinary high water level, 75 feet from elevation 929.4, or 70 feet from any shoreline improvement such as riprap, a seawall or retaining timbers. Where surveys disagree, the one producing the greatest setback governs.
The fourth is timing. Building permits issue no sooner than ten business days after application, a certified site survey is required, and the city maintains a construction management ordinance governing how work is carried out. On a project with a septic inspection in front of it, the approvals can take longer than a phase of the build.
Home » Whole-Home Remodeling in Woodland
Home » Whole-Home Remodeling in Woodland
More services in Woodland
If an addition is in scope and you are on a private system, the septic inspection and the ten-day permit hold set your realistic start date. Better to build the schedule around them from the beginning than to meet them halfway through.
You get a written scope and a fixed price before demolition starts. Licensed, bonded and insured in Minnesota, #BC800584.